When attaining and assigning resources to the project (given that you can use both internal and external resources), you plan to hire your external resources using a work order against a contract between you and a local staffing agency. Which of the following statements is NOT true in this scenario?

A The team members coming from the consulting company are accounted for in the Plan Procurement Management process and Plan Resource Management process, not this process.
explanation

All resources for the project, both existing staff members and consultants or external staff, are taken into consideration in the Acquire Resources process. While the procurement process's function is to recruit staff members, the Acquire Resources process involves attaining and assigning resources.