When expressing his concerns over the schedule in a team meeting, Nick was cut off repeatedly by John, who felt that the focus of the meeting should be the recent server crash. This resulted in Nicks' dissatisfaction and he left the meeting. What went wrong?
A
The project manager had not set clear ground rules.
explanation
Even though John felt that Nick’s issue was not as urgent, all issues should be allowed to be brought to the table or through the outlined procedures.
Comments