Question:

When it comes to dealing with risk, the project manager A has a difficult time with the department manager B. The department manager B does everything possible to avoid risk, even if it negatively impacts the project. What type of risk attitude does the department manager B have?

A Risk averse.
explanation

The names of the risk attitudes are fairly descriptive, which makes it easy to understand them at face value. All of the listed options are risk attitudes. However, the "risk averse" option best describes the manager B's risk attitude.