Which of the following statements is NOT true about the tools and techniques of the Control Schedule process?

A Delays to noncritical path activities will not cause schedule delays.
explanation

Unless one or more of the non-critical path activities have used up all of their float time, schedule delays will only be caused by critical path activities. The question doesn't specify that a noncritical-path activity has used all its float time.