Which process does NOT belong to the Project Integration Management Knowledge Area?

A Identify Stakeholders.
explanation

The Project Integration Management Knowledge Area contains the following processes: Develop Project Charter, Develop Project Management Plan, Direct and Manage Project Work, Manage Project Knowledge, Monitor and Control Project Work, Perform Integrated Change Control, and Close Project or Phase. The Project Stakeholder Management Knowledge Area is concerned with identifying stakeholders.