Question:

You are managing a project for a construction company. The project is to construct a new city and build a county office building in your local. A scope change has just been approved by your CCB. What is NOT a cause of the mentioned scope change?

A Schedule revisions.
explanation

Scope changes will result in schedule revisions, but schedule revisions have no effect on the project scope.