Question:

You are managing a project of developing a new line of bath products for Ooh La La Beauty Products. You are also working on the CCB, by which a scope change has just been approved. Which of the following statements is NOT true regarding your situation?

A Scope changes do not usually impact the project budget.
explanation

Scope changes potentially impacts the schedule, cost, quality, and other processes; therefore they should be thoroughly integrated with all the Monitoring and Controlling processes. Scope changes may lower the project requirements down, as a result they would shorten the project duration. This, in turn, could make the project budget lower than scheduled.