header bg

Scan QR code or get instant email to install app

Question:

You are managing the Kitchens Plus' latest project which are developing an automatic dicer with unique industry features. The budget for this project is $95,000. The project has a planned value of $70,200, an earned value of $59,000, and an actual cost of $65,500, based on the latest data. According to the schedule and budget, what is the project's status?

A The project is behind schedule and over budget.
explanation

To answer this question, you will need to calculate the cumulative SPI and CPI using all of the provided values.
-Calculating SPI:
The formula for calculating SPI is:
SPI = EV ÷ PV.
Plug in the provided values, we have: ($59,000 / $70,200) = 0.84.
=> 0.84 < 1.0 => The project is behind schedule.
- Calculate CPI:
The formula for calculating CPI is:
CPI = EV ÷ AC.
Plug in the provided values, we have: ($59,000 / $64,500) = 0.91.
=> 0.1 < 1 => The project is over budget.
Therefore, the project is behind schedule and over budget.

Related Information

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *

*