Scan QR code or get instant email to install app
Question:
To answer this question, you will need to calculate the cumulative SPI and CPI using all of the provided values.
-Calculating SPI:
The formula for calculating SPI is:
SPI = EV ÷ PV.
Plug in the provided values, we have: ($59,000 / $70,200) = 0.84.
=> 0.84 < 1.0 => The project is behind schedule.
- Calculate CPI:
The formula for calculating CPI is:
CPI = EV ÷ AC.
Plug in the provided values, we have: ($59,000 / $64,500) = 0.91.
=> 0.1 < 1 => The project is over budget.
Therefore, the project is behind schedule and over budget.
Comments