You are working as a project manager for Lightning Bolt Enterprises. Your latest project aims to research and develop a new type of rechargeable battery. One of your stakeholders requests a change to the product scope description. He has filled out a change request form indicating that the change is essential for the project's success. The change request is approved, and the project scope statement is updated to reflect this change. Which of the following statements is INCORRECT?

A The product scope description, which is also a component of the project charter, is used to define the project’s scope.
explanation

The product scope description is not a component of the project charter. The product scope description is a part of the project scope statement, which is a separate document from the project charter. The project charter provides an overall high-level description of the project objectives, stakeholders, and authority granted to the project manager. The project scope statement, on the other hand, provides a detailed description of the project's deliverables, objectives, and the work that needs to be done to accomplish those objectives. It also includes the product scope description, which describes the features, functions, and characteristics of the product or service that the project aims to deliver.

Related Information

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *

*