Question:

You are working for an engineering company as a project manager. Your company won the bid to add ramp-metering lights to several onramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project (which involved digging the holes and setting the lamp poles in concrete) to another company. You’ve discovered the poles were not buried to the correct depth led by the subcontractor's error. After reviewing the work, you noted the gaps in the process and a lack of safety standards as a result of this error. Which of the following statement is true?

A You are in the Manage Quality process and have performed a quality audit and identified a need for a corrective action.
explanation

In project management, the Manage Quality process is responsible for ensuring that the project deliverables meet the required quality standards and specifications. It involves auditing the quality of work, identifying deviations from standards, and taking corrective actions to ensure the project meets the desired quality requirements.

Related Information

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *

*