header bg

Scan QR code or get instant email to install app

Question:

Your project has started, and you are initiating a series of overview sessions with key users to gather requirements for a new enterprise resource software implementation. One of your stakeholders is quite contentious and creates obstacles at every opportunity. One of the problems she has described appears to be legitimate. Before progressing further, an issue with the data from the legacy system needs to be resolved. The Project Management Office (PMO) you report to follows phase sequencing and requires the closure of each phase before commencing the next phase. Select all names of this process.

A Phase review.
explanation

According to the PMBOKĀ® Guide, this process is called stage gates, phase reviews, phase gates, phase exit, or kill points.

Related Information

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *

*