You are working on a top priority project for your organization. One key stakeholder decided to resign, and her replacement started about three weeks ago. She did not make time for you or seemed to have the same level of urgency about this project as the CEO. You were concerned with overall project success and wanted to efficiently manage the processes involved with this project. Which of the following best describes this situation?

A Monitoring stakeholder engagement.
explanation

The described activities in this question are related to monitoring stakeholder engagement, which is part of the Monitor Stakeholder Engagement process. Keeping stakeholders engaged will help project success and keep them up to date on issues and status.