Question:
Total float is the amount of time you can delay the earliest start of an activity without affecting the scheduled deadline. To calculate total float:
Step 1: Draw a network diagram then perform a forward and backward pass.
Step 2: Subtract either the early start from the late start or the early finish from the late finish (both should give you the same answer).