Question:
The Plan Procurement Management process involves the requisition stage in which the procurement documents are prepared (not the responses to them). Procurement documentation and source selection criteria are the two outputs that become inputs.
The award stage is related to the Conduct Procurements process because it is the process of awarding the contract to the selected supplier. The requirement stage is related to the Plan Procurement Management process because it is the process of defining the project and contract needs.
Two of the outputs of the Plan Procurement Management process are inputs to the Conduct Procurements process. These outputs are the procurement documentation and the procurement plan. The procurement documentation includes the request for proposal (RFP), the request for quotation (RFQ), and the contract. The procurement plan includes the procurement strategy, the schedule, and the budget.