John was late for the weekly morning project meeting and had to dial into the phone bridge to join the meeting. Unfortunately, he was too late to join in the discussion about the topics that were of interest to him. Therefore, he sent an email to the chairman of this meeting to ask if he would be provided with the notes for the meeting via email or whether these notes would be placed on the team wiki site. When used for sharing information, meetings, email, web publishing, and telephone are some examples of ________.
A
Information management systems.
explanation
The mentioned means of communication are examples of project management information systems - a tool and technique of the Manage Communications process.