Question:

The Monitoring and Controlling process group has several processes that involve change requests. Which of the following statements is INCORRECT?

A Approved change requests are an output of the Perform Integrated Change Control and Monitor Risks processes.
explanation

Approved change requests are an output of the Perform Integrated Change Control process but not of the Monitor Risks process.