The project team has recently participated in a working session to determine the costs associated with individual activities. They broke each activity down into smaller chunks to conduct a more accurate estimate. What process is the team engaged in?
A
Estimate Costs.
explanation
The team is carrying out the Estimate Costs process to develop an approximation of the cost of resources needed to complete project work.